The cathedral sanctuary is taking shape at the corner
of Grand Avenue and Harrison Street. High above the sanctuary floor,
a steel oculus is being welded together. The skylight ceiling will
be assembled on top of the oculus ring. JOHN
BLAUSTEIN PHOTO |
 |
| This artist rendition shows the completed cathedral
with the grand staircase leading to the sanctuary from Harrison Street.
To the left is an entrance to the conference center. Parish offices
are to the right of the staircase. |
 |
Over several weeks construction workers built a
giant shoring tower of scaffolding over the sanctuary floor and circular
altar. The oculus roof is assembled at the top of the tower and the
rest of the cathedral superstructure will be built from the roof down.
JOHN BLAUSTEIN PHOTO |
 |
The catafalque area for funeral services in the
mausoleum is directly under the altar. Light enters through the oculus
of the cathedral and continues through the transparent glass floor
of the altar into the mausoleum.
JOHN BLAUSTEIN PHOTO |
By Bill Utic
Chairman, Finance Committee
The Cathedral of Christ the Light
Within the
past few weeks several letters have appeared in The Catholic Voice regarding
the cost of the Cathedral Center. I would like to provide additional information
about its scope and budget.
As Bishop Allen Vigneron has shared previously in The Voice, the Cathedral
Center is a pastoral response to the needs of the diocese and community.
The many volunteers and professionals contributing to the project have
worked diligently to realize this vision in a responsible manner.
As the project has progressed through each step of design, engineering
and construction, the budgeting information available to us has improved
as preliminary design estimates have been replaced with actual construction
drawings and contracted costs. This has required a restatement of the
project budget.
The project scope, that is, the major components planned for the Cathedral
Center, includes the cathedral and organ, public plaza, mausoleum, conference
center, parish offices, parish rectory, bishop’s residence, parking
garage and Chancery offices.
The master plan for the Cathedral Center site includes a bell tower and
daily chapel, but these components are not part of the project scope and
will not be built at this time.
The project budget for the Cathedral Center has increased from an early
estimate of $131 million in 2003 (based on very early conceptual plans
that contained assumptions and allowances for costs not yet known) to
a current estimate of $190 million in January 2007.
The current budget estimate includes all costs associated with the Cathedral
Center, including insurance, property taxes, fundraising, diocesan administration,
financing and other “non-construction” costs.
In 2003, only two percent of the project costs had been bid out and priced.
Several experienced construction estimating firms were used to help establish
the initial $131 million budget estimate, but actual pricing could not
be obtained until design and construction drawings were completed and
submitted to contractors and suppliers for bids.
The unique design of the cathedral, which employs state-of-the-art technology,
did not allow the use of comparable costs from other construction projects
for estimating purposes.
The organ and mausoleum were not included in the $131 million budget estimate,
even though they have always been part of the project scope, because separate
funding sources were planned for them.
An unintended consequence of separate budgets for the organ and mausoleum
has been confusion about the cost of the project. In an effort to avoid
further confusion between project scope and project budget, the $190 million
estimate includes the organ and mausoleum.
Bishop Vigneron’s message in the January 8, 2007 Voice noted that
the conference center was not included in the project budget when construction
began in 2005. Finishes, furniture and equipment for the conference center
were deferred until future funding (such as unused project contingency)
became available.
However, because of the conference center’s important role in supporting
the mission and activities planned for the Cathedral Center, the full
cost of the conference center has been included in the $190 million budget.
The $131 million budget estimate at the time construction began in June
2005 was comprised of the following components:
Land costs - $32.7 million
Design, project management and other professional fees - $12.8 million
Construction costs - $67 million
Furnishings, fixtures and other equipment - $5.5 million
Financing costs - $3 million
Fundraising, administration and legal costs - $4.7 million
Contingency - $5 million
The $190 million budget estimate contains the following additional costs:
Mausoleum (previously in scope but separately budgeted) – $13.1
million
Organ (previously in scope but separately budgeted) - $4.0 million
Conference center completion - $2.4 million
Unforeseen site excavation conditions and weather delays - $2.7 million
Inflation - $5.5 million
Miscellaneous design revisions - $3.8 million
Additional design, project management and professional fees - $3.2 million
Additional insurance, inspection and permit fees - $1.1 million
Additional furnishings, fixtures and equipment - $0.7 million
Additional financing costs - $8 million
Additional fundraising, administration, legal and taxes - $3.7 million
Additional contingency - $10.8 million
Some of these costs, such as design, project management and other professional
fees, insurance, inspection and permit fees, financing and administration
have increased in part because of higher construction costs and extension
of the estimated project completion date from late 2007 to the third quarter
of 2008.
Contingency is an allowance for costs that may not be incurred, such as
construction delays, design problems, unforeseen permit conditions and
other challenges typically encountered in construction projects of this
complexity.
Contingency is not expended unless needed and unused contingency will
reduce the final project cost.
Because the project is now 50 percent completed and 95 percent of the
total construction cost is priced and under contract, the Project Finance
Committee believes that further budget increases are unlikely. |
|
|